HVACCalc.

Insulation R-value calculator

The R-value your climate zone calls for in an attic, floor or wall, the R you still need to add, and the depth of material that represents — with the air-sealing work that has to come first.

The result below is the worked example already filled in. Change a field and press the button to see your own numbers; the result updates in place.

Your answer

Add R-41

attic floor in zone 5 — cool · target R-60 · about 11.7 in of blown cellulose

What you have R-19 Depth × R per inch, or the label on the batt
Recommended target R-60 ENERGY STAR retrofit table for this climate zone
R-value to add R-41 60 − 19
Depth of new material 11.7 in blown cellulose at about R-3.5 per inch
R per inch used R-3.5 Typical installed value; the bag or datasheet is the authority
Where the target comes from Zone 5 — cool Boston MA, Chicago IL, Denver CO
  • Zones 4 and colder target R-60 in an attic; zones 2 and 3 target R-49; zone 1 targets R-30. This is zone 5 — cool.
  • Depth is arithmetic from a typical installed R per inch. Settling, compression and framing all reduce what you actually get.

Before you buy

  • Air sealing comes before insulation. A half-inch gap around a chimney or a top plate moves more heat than an extra R-10 of attic insulation saves.
  • Never cover recessed light fixtures unless they are rated IC, and keep insulation 3 inches away from flues and chimney walls.
  • Do not compress the insulation to make it fit. Compression lowers the R-value per inch, which is why a 2×4 wall cannot reach R-21 without continuous insulation.
  • In an attic, keep a clear path at the eaves so the roof can breathe. Baffles are cheap and a mould problem is not.
  • Check the joist depth before you blow insulation in: loose fill above the joists is fine, but you need to be able to find the joists to walk safely.

What R-value measures

R-value is thermal resistance: how well a material slows heat passing through it. Higher is better, and the R-values of layers add up, so a wall with R-13 cavity insulation and R-5 continuous sheathing is roughly R-18 before framing is counted. Framing matters: studs, joists and headers conduct heat around the insulation, which is why the whole-assembly R-value is lower than the number printed on the batt.

The targets below are retrofit recommendations from the DOE and ENERGY STAR tables, keyed to the eight IECC climate zones. They are not code minimums for new construction, and they are not a promise about your energy bill. They are the level at which additional insulation usually stops paying for itself quickly.

The targets by climate zone

ZoneExample citiesAttic targetFloor targetWall cavity target
1Miami FL, Honolulu HI, San Juan PRR30R13R13
2Orlando FL, Houston TX, Phoenix AZR49R13R13
3Atlanta GA, Dallas TX, Los Angeles CAR49R19R20
4Philadelphia PA, Nashville TN, St. Louis MOR60R19R20
5Boston MA, Chicago IL, Denver COR60R30R20
6Minneapolis MN, Milwaukee WI, Burlington VTR60R30R20
7Fargo ND, Duluth MN, Caribou MER60R38R20
8Fairbanks AK, Utqiaġvik AKR60R38R20

Two notes on the wall column. First, older guidance for zone 1 and zone 2 lists no wall recommendation for a retrofit, because the attic is where the savings are; R13 is the practical cavity fill and is shown for reference. Second, from zone 3 upward the code path is cavity insulation plus continuous insulation outside the sheathing — R5 in zone 3 and R5 to R10 in zones 4 to 8. A 2×4 cavity cannot reach R-21 on its own, no matter what the label says.

Measuring what you already have

In an attic, measure the depth of the insulation with a ruler in several places, without compressing it. Blown cellulose is typically R-3.1 to R-3.8 per inch, loose fiberglass R-2.2 to R-2.7, fiberglass batts R-2.9 to R-3.8, and mineral wool R-3.1 to R-3.4. A 6-inch layer of cellulose is therefore about R-21, not R-30. If the depth is uneven, use the shallowest measurement: that is where the heat escapes.

In a wall, the honest answer usually requires a hole. A 2×4 wall with batts is R-13 to R-15; a 2×6 wall is R-19 to R-21. If the wall is empty, it is R-0 plus whatever the sheathing and drywall contribute, which is very little. A contractor can confirm with a borescope or by removing a receptacle cover.

Air sealing comes before more insulation

Insulation slows conductive heat flow. Air leaks move heat with the air, and no amount of R-value stops a draught. The classic leaks are the top plate, the chimney chase, recessed lights, plumbing penetrations, the attic hatch and the rim joist. Sealing them is inexpensive and is usually the highest-return hour of work in an old house.

Order matters: air seal, then insulate. Blowing insulation over an unsealed attic makes the leaks harder to find and can make a moisture problem worse. The DOE guide is explicit that air sealing and moisture control belong with the insulation decision, not after it.

Depth, compression and the details that ruin a good R-value

Loose-fill insulation does not gain R in perfect proportion to depth, because the weight of the material compresses the bottom layers. Compressed batts lose R the same way: a 2×4 cavity stuffed with an R-19 batt does not deliver R-19. The calculator multiplies the R you need by a typical installed R per inch, which is why the depth it shows is a planning number, not an order.

In an attic, keep a clear path at the eaves for ventilation, use baffles, and keep insulation away from flues and chimney walls. Do not cover non-IC recessed lights. In a floor over a crawlspace, support the insulation so it stays in contact with the subfloor and fit a vapour barrier on the warm side according to your climate. In a wall, the cavity has to be dry before it is filled.

Vapour, moisture and the order of operations

In a cold climate the vapour barrier goes on the warm side of the insulation; in a hot, humid climate the rule is often the opposite, and getting it wrong traps moisture in the assembly. This is the part of insulation work most likely to cause a expensive problem, and it is the part a calculator cannot see. If you are insulating a wall or a cathedral ceiling rather than an open attic floor, have the assembly reviewed by someone who knows your climate.

Wet insulation is worse than no insulation: it conducts and it feeds mould. Fix the roof leak, the grading and the dryer vent before adding material.

What this calculator cannot tell you

It does not know your assembly, your framing fraction, your air leakage rate or your existing moisture profile. It uses zone-level targets, and a house at 5,000 ft or on a marine coast may be a zone off. It cannot price the work, because insulation prices vary by region and by access, and this site does not publish prices at all. It also cannot tell you whether the attic has enough ventilation, which is a separate requirement.

Use it to size the project and to check a contractor’s proposal. If a quote proposes R-30 in a zone 5 attic, ask why it is below the DOE target. If it proposes R-80, ask what the extra R is expected to save.

Frequently asked

What R-value do I need in my attic?

Zone 1 targets R30, zones 2 and 3 target R49, and zones 4 and colder target R60 in the ENERGY STAR retrofit table. The target is the total assembly R-value, not the amount you add: if you already have R19, you need about R41 more.

How many inches of insulation is R-49?

About 14 inches of blown cellulose at R-3.5 per inch, or about 20 inches of loose fiberglass at R-2.5 per inch. Batts are denser, so R-49 takes fewer inches but is harder to fit around obstructions.

Can I put insulation over old insulation?

Usually yes, if the old insulation is dry, intact and not vermiculite. Do not put a vapor barrier on top of an existing one in a cold climate, and never cover recessed lights unless they are rated for contact with insulation.

Does a higher R-value always save money?

No. The first inches save the most; each additional inch saves less because the temperature difference across the assembly is already small. The targets here are cost-effective retrofit levels, which is why zone 1 stops at R30 while zone 6 goes to R60.

What is the difference between R-value and U-value?

R-value measures resistance to heat flow and higher is better. U-value is its reciprocal, a measure of conductance, and lower is better. Windows are usually rated in U-value, insulation in R-value.

Should I insulate the walls or the attic first?

The attic, almost always. It is accessible, the work is inexpensive per unit of R, and heat rises. Walls are worth doing when siding is off or during a gut renovation, because blowing a cavity is cheap then and expensive later.

Where these numbers come from

Numbers that come from our own arithmetic rather than a published table are marked house rule on the method page. No price appears anywhere on this site: no supplier publishes a national one, and an invented number would be worse than no number.

Next: BTU calculator · furnace size · heat pump size · method and sources